Down to Size

Aug. 8, 2018
Grinder cuts $78,000 from energy costs in Santa Margarita (Calif.) Water District

When the Santa Margarita (Calif.) Water District (SMWD) was formed in 1964 by a group of ranchers who wanted a reliable water source for their cattle, the district served more cows than people. Since then, the area has grown to over 150,000 homes and businesses, and the SMWD maintains more than 1,200 miles of water and sewer lines across a 62,674-acre service area. Keeping up with both the water and sewage disposal needs of the community has come with significant challenges, particularly due to both the increase in influent and the change in the makeup and durability of the sewage running through the district’s reclaimed-water facility.

The problem

Built in 1977, the reclaimed-water facility was initially intended to provide water for landscape irrigation in the district. During a typical 12-month period, the facility brings in 680 million gal of sewage and sends out 620 gal of reclaimed water. Originally, the facility relied on a mechanically cleaned bar screen to remove debris from the waste system. Over time, safer, more reliable solutions came on the market, and the bar screen was replaced by a CMD single-drum Channel Monster from JWC Environmental that would shred debris before it reached the pumps, preventing clogs or damage. Pump clogging hadn’t been an issue since the Channel Monster was installed in the ’90s—until two years ago, when the composition of the influent became heavily loaded with disposable wipes.

“We have a bank of four VFD-controlled pumps at the facility, and typically we run an alternating cycle with two pumps operating and then switching to ensure equal runtime for all the pumps,” said Ron Johnson, facilities supervisor for the SMWD facility. “This operating sequence with the pumps modulating around 50 Hz kept up with plant flow requirements. But starting in about 2012, the pumps would begin to lose efficiency as the wipes loading increased, and we would have to run all four pumps to maintain plant production. Once they reached 60 Hz, we would need to shut down the plant to de-rag the pumps.”

The de-ragging process started to become necessary every two to six weeks, requiring two operators for about two hours each time to complete the task.

“And due to some aging isolation valves that leaked, the plant needed to be entirely shut down during de-ragging,” said Johnson.

These unplanned shutdowns were costing the district an acre-ft of reclaimed water production per month, and the labor costs added up to about $15,000 per year. Beyond the mounting monetary cost, the safety concerns were equally troubling.

“The most efficient method of removing rags is to pull them through the inspection port as one large ball,” said Johnson. “But this procedure, besides being unpleasant, exposes a worker to potential sticks from sharps in the rag balls.”

Johnson began looking for a long-term solution to the ragging problem, since both the cost and safety concerns were not sustainable for the district.

“We considered changing out the current pumps to a new set of chopper pumps, but this option came with a $100,000 price tag and wasn’t really going to solve the problem,” said Johnson. “We still needed to maintain our inlet Channel Monster to take care of the larger debris the pumps couldn’t handle.”

The solution

Johnson ultimately decided to upgrade the facility’s Channel Monster to a new perforated metal drum configuration. The coil drums of the original Channel Monster were designed to capture large debris and push it into the grinder’s cutter stack for size reduction. As sewage has evolved and non-dispersible wipes have become a major part of the waste stream, the infrastructure to deal with it has needed to change as well. The perforated drum on the newest generation of Channel Monsters was designed to better capture the wipes and rags that flow through traditional coil drums.

“This upgrade cost significantly less than purchasing a whole new set of pumps,” said Johnson. “Plus, this is a solution that will completely eliminate the pump-clogging problems we were having for the long term.”

The results

Since the new Channel Monster drums were installed, the district has had no pump-clogging issues at the facility and has returned to using two pumps at a time instead of all four. Energy costs have decreased $78,000 per year, and manual pump de-ragging has been eliminated.

“While the cost savings and the eliminated safety risks are quantifiable, our choice to go with a new Channel Monster, to me, is priceless,” said Johnson.

Kevin Bates is the global marketing director for JWC Environmental.

About the Author

Kevin Bates

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Chemical Plant Case Study

Aug. 14, 2024
Chemical Plant Gets a Fiberglass Conduit Upgrade

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.