Standing Up to the Elements

Aug. 17, 2018
Missouri water project uses customized precast concrete buildings designed to resist 180-mph winds

Missouri American Water (MAW), a regional division of American Water Works Co., serves 1.5 million people in more than 150 Missouri communities. With such an expansive reach, maintaining equipment is essential. At its Central Water Treatment Plant in Maryland Heights, outside of St. Louis, a major replacement was needed for an existing pump station built in the 1930s because of hydraulic limitations to operational needs.

With a focus on cost savings and a tight schedule, MAW utilized two new Easi-Span precast concrete buildings as part of the renovations at two plants—a 28-ft-by-40-ft-by-13-ft electrical building for the new pump station at the Central plant, and a 27-ft-by-38-ft-by-13-ft switch gear building at the North plant in Florissant, Mo. The Easi-Span buildings are the largest clear span all-concrete buildings on the market, and the only expandable concrete building systems. These buildings feature clear-span roofs up to 50 ft by 250 ft and heights up to 35 ft. Smaller Easi-Set buildings can be delivered completely erected and pre-outfitted, ready for use after utility hookups are made.

Carollo Engineers of Kansas City, Mo., led the engineering for the Central plant, and Ross & Baruzzini of St. Louis led the engineering for the North plant. The Central plant facility is a 52.5-mgd firm-capacity high-service pump station with a 30-ft-deep wet well. Its operation requires four vertical turbine pumps, soft starters, a variable frequency drive, medium voltage switchgear, new automation controls, a 48-in. diameter discharge header and 42-in. transmission main. Goodwin Brothers Construction of Crystal City, Mo., constructed the pump station, and it selected McCann Concrete Products Inc. of Dorsey, Ill., to manufacture the precast building. McCann Concrete is one of 70 licensed producers of Easi-Set Worldwide.

The Easi-Span building, which is available with monolithic precast floors, was set on a cast-in-place concrete foundation for this application. The 12 wall panels are 5 in. thick and match existing structures at the site.

“We precast the walls with the Easi-Brick system and matched the wall panel to the older brick buildings on site,” said Mark Melvin of McCann Concrete.

The client asked for the building to have a 180-mph wind load, which McCann Concrete was able to supply by customizing the structure. For the interior, insulation was added, and the walls have a plywood finish. Any penetrations less than 2 in. in diameter were field-drilled on site; larger ones were cast. The shell of the building was erected in just three days, and the interior finishing took an additional three.

While there were no issues with the building construction, the project team did have challenges to overcome.

“The project site is located in the floodplain of the Missouri River,” said Jennifer Meyer, P.E., senior project engineer for MAW. “Due to subsurface conditions in the project area, extensive ground improvements were required to protect the new structures, as well as mitigate the construction risk associated with the groundwater table in the project area. Construction limits are surrounded by in-service 24- and 36-in. transmission mains, operating at nearly 200 psi and dating back to 1910, the 1920s and 1930s. Integrating this new pump station with the existing 217-mgd treatment plant and distribution facilities was a complex task.”

When reviewing materials for water and wastewater applications, Melvin suggests pre-cast concrete simply because buildings can be adapted to meet the specifications of a project—and because it will last.

“It is very durable and provides the owner with a long-lasting building,” he said. “We can customize our solutions as well. In this case, we were able to design to wind loads of 180 mph, which provides protection for the expensive equipment inside the building.”

About the Author

Easi-Set Industries

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Chemical Plant Case Study

Aug. 14, 2024
Chemical Plant Gets a Fiberglass Conduit Upgrade

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.