Station Arrival: Storm Water Management

April 2, 2018

About the author: Mike McGough, P.E., is chief engineer for the National Corrugated Steel Pipe Assn. McGough can be reached at [email protected]. Jerome S. Silagyi, P.E., is manager of technical services for Lane Enterprises, Inc. Silagyi can be reached at [email protected].

undefined

Located in the Olney neighborhood of Philadelphia, the SEPTA R8 Fox Chase Line facility now has somewhat of a resurrection story in its 100-year history. Originally constructed by the Reading Co. in 1906, the Olney train station was decommissioned when the Southeastern Pennsylvania Transportation Authority (SEPTA) ceased allowing customers to use the station in the 1980s. In June 2008, the station was demolished to make way for a new facility with high-level platforms. However, building requirements have changed dramatically over the past century, most notably those pertaining to storm water management.

What once would have been an impossible task to accomplish for a small site that hosts some 60 parking spaces has become possible with the advent of underground storage systems. Over the past couple of decades, the traditional detention pond has given place to buried storm water management systems that preserve operational functionality of the much-needed space in the heart of urban development, or in this case, urban redevelopment.

In this vein, corrugated steel pipe (CSP) has found new life and become the leading option available for engineering designers availing themselves of the strength, service life, constructability and size range afforded by this engineering material.

SEPTA’s multidisciplined engineering department was able to provide cradle-to-grave site development, beginning with conceptual design and ending with construction management. The reviewing agency responsible for storm water management was the Philadelphia Water Department, who quickly assigned a restricted storm water discharge to mitigate an outlet that had become overtaxed through the years. The restricted storm water discharge assignment necessitated a detention requirement in excess of 15,000 cu ft.

Coated CSP for the Century
With limited area to accommodate this amount of storage, SEPTA engineers decided on a 7-ft-diameter CSP storm water management system with an overall dimensional footprint of 94 ft by 37 ft. Of particular interest is the type of CSP specified by the SEPTA design engineers: polymer-coated CSP.

Polymer-coated CSP was selected for its design service life of 100 years. Of the three major coating types available in the CSP market today (galvanized, aluminized and polymerized), polymer-coated CSP provides the greatest service life and is the premier coating available.

The polymer coating consists of a 10-mil polymer film that is laminated over each side of a galvanized steel coil prior to the pipe manufacturing process. The Trenchcoat protective film is a tough, rugged polyolefin laminate that provides galvanized CSP with a durable barrier that exceeds the corrosion and abrasion resistance of all other coatings.

Another feature of utilizing CSP for underground storage purposes is the ability of the pipe manufacturer to fabricate fittings, manifolds, access risers, flow control structures and any other appurtenances needed to support the hydraulic functions or maintenance of the system. Fabrication is accomplished with experienced welders using the very material specified for the storm water management system—in this case a 7-ft-diameter polymer-coated CSP.

To provide the most efficient use of the available storage and minimize potential clogging, a 3-in. conical, stainless steel vortex valve was used to meet the discharge limit requirements. As part of the detention system’s outlet, the valve was easily fastened to a 7-ft-diameter bulkhead.

Unlike an orifice, vortex control increases as the pressure builds, having little control initially and maximum control once the design head is reached. This feature allows the valve to be oversized without exceeding the discharge limit when the system is full.

Station Resurrected
The storm water management system was assembled easily. The facility was located less than 20 miles from the project site. A just-in-time delivery procedure helped manage a very space-limited site and allowed the contractor, D’Angelo Bros., to better manage ingress and egress from one end of the site to the other.

Aside from providing customer parking, SEPTA’s construction management team was able to maintain functionality of the Olney Station for its users; evidence of the station’s need presented itself with the numerous neighborhood residents walking to and from the site throughout each day during the construction process. The resurrected facility is teeming with new life and prepared for a century of use.

Download: Here

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.