Floor Doors, Safety Posts Included In Elaborate Project at VA Hospital

Sept. 28, 2020

Edward Hines Jr. VA Hospital in Chicago included 15 floor access doors manufactured by BILCO.

Floor access doors and LadderUP ® safety posts from The BILCO Company were included in the construction of an elaborate central utility plant at the Edward Hines Jr. Veterans Administration Hospital near Chicago.

The new plant replaced a nearly-century old system at the hospital, which opened in 1921. After a nine-year design and construction process, the new plant opened in 2019.

Architects started design on a new boiler plant in 2009, but flooding in 2010 of the Des Plaines River took out the existing boiler plant and exposed a major flaw in building a boiler plant below grade. The flooded plant was drained and existing systems repaired to allow the campus to remain operational until a new plant could be designed and constructed.

After years of design, government-requested cost-saving changes and 242 drawings submitted by architects, work on the new plant started in 2016. The scope of the project included the installation of four new boilers, an emergency diesel generator, and the construction of an underground steam distribution system.

“We worked with the design team and needed to install all new equipment,” said Mike Deis, the senior project manager for The Walsh Group, the general contractor for the project. “Some of the buildings had deteriorated during the flood. The distribution system was directly buried, and was not enclosed in a concrete tunnel. All the tunnels needed to be replaced for the steam system on the campus.”

The project includes 15 BILCO floor doors. They are frequently found in exterior applications where there is a concern of liquids entering the access opening. The doors include a channel frame, aluminum frame and engineered lift assistance for one-hand operation. Illinois Construction Specialties procured the doors for Walsh.

Workers ascend and descend on ladders equipped with 15 LadderUP® safety posts, also manufactured by BILCO. The safety posts feature a telescoping design that is spring balanced for easy operation and includes adjustable mounting hardware that accommodates virtually any ladder rung size or spacing.

“We do quite a bit of work with BILCO for this application, especially in maintaining a fire rating of if there is a tank underground,” Deis said. “They service the entire country, and we do work all across the country. We know that we can count on them to service this product.”

The hospital recorded more than 850,000 patient visits during the fiscal year in 2017, providing care to more than 57,000 veterans from three counties in the area. It was listed in the National Register of Historic Places in 2013 and is named after the son of Chicago lumber magnate Edward Hines, who purchased the property in 1917. Edward Hines Jr. died while serving on the front lines in France during the opening months of World War I. The hospital was the first VA hospital to be named after a person.

Editor's Note: Scranton Gillette Communications and the SGC Water Group are not liable for the accuracy, efficacy and validity of the claims made in this piece. The views expressed in this content do not reflect the position of the editorial teams of Water & Wastes Digest, Water Quality Products and Storm Water Solutions.

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Chemical Plant Case Study

Aug. 14, 2024
Chemical Plant Gets a Fiberglass Conduit Upgrade

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.