AnoxKaldnes IFAS: Meeting New Limits

Sept. 18, 2019

Field's Point Wastewater Treatment Facility uses IFAS process to reduce total nitrogen and meet strict standards.

The Narragansett Bay Commission owns and operates the Field’s Point Wastewater Treatment Facility (FPWWTF) in Providence, R.I. The commission’s service area encompasses the metropolitan Providence and Blackstone Valley areas. Originally constructed in 1901, the FPWWTF provides secondary treatment for maximum monthly flows of up to 77 mgd and primary treatment and disinfection for an additional 123 mgd of wet weather flows; the total treatment capacity at the FPWWTF is 200 mgd.

The Solution

After receiving a National Pollutant Discharge Elimination System (NPDES) operating permit that required the plant to remove total nitrogen (TN) to 5 mg/L from May to October, the Narragansett Bay Commission chose AnoxKaldnes Hybas (Hybrid Biofilm Activated Sludge), an integrated fixed film activated sludge (IFAS) process as its solution.

In 2008, Veolia completed AnoxKaldnes Hybas designs for the upgrade of the FPWWTF to meet new seasonal effluent limits for TN and total inorganic notrogen. The AnoxKaldnes Hybas process has the advantage of accepting a significant combined sewer overflow while maintaining a nitrifying biomass and eliminating the need to construct new aeration basins on a constrained site.

Process Description

The FPWWTF project involved process design, equipment supply, training, in-field services, performance testing and guarantees related to the AnoxKaldnes Hybas process. The biological nutrient removal process included the following unit processes:

  • Pre-anoxic stage with two reactors per train for denitrification using the influent biological oxygen demand (BOD) as a carbon source and return mixed liquor from the aerobic stage for the source of nitrate;
  • Aerobic nitrification stage with IFAS and post-IFAS oxic zones for BOD and nitrification;
  • Post-anoxic stage with two reactors per train for additional denitrification using an external carbon source (if needed); and
  • Re-aeration stage for removal of any residual carbon source and nitrogen gas stripping.

The Results

The IFAS conversion was accomplished without the need to add secondary clarifier capacity. FPWWTF has begun operation as the largest IFAS system in the world.

Sponsored Recommendations

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Meeting the Demands of Wastewater Treatment Plants

May 24, 2024
KAESER understands the important requirements wastewater treatment plant designers and operators consider when evaluating and selecting blowers and compressed air equipment. In...

Modernize OT Cybersecurity to Mitigate Risk

April 25, 2024
Rockwell Automation supports industry-leading Consumer Packaged Goods company, Church & Dwight, along their industrial cybersecurity journey.