Bypass System at Pump Station Enables Upgrade Completion

Nov. 8, 2018

Custom-designed solution offers project team remote bypass control & monitoring

The West Side sewage pump station in Onondaga County, N.Y., required a bypass system to move a peak flow of 30 million gal per day (mgd) during its first major upgrade in more than 30 years. C.O. Falter Construction was named the bypass contractor for the project and worked with Xylem to design and install a temporary system to convey the full amount of flow.

The West Side pump station is the second-largest pump station in Onondaga County, taking in about 8 mgd of sewage from communities in the western suburbs and then pumping it to a nearby wastewater treatment plant. The expansion and upgrades to the station would add more sewer capacity to help reduce sewage overflows into Lake Onondaga during heavy rains. The project also would expand the pump station’s capacity and increase its efficiency.

Scope

While the initial design called for using the station’s existing pumps, a dewatering application engineer with Xylem calculated during a plan review that the existing pumps would only bear 19 mgd of water. 

“After determining that the initial design missed the target by 25%, it became apparent the job would require a temporary bypass system to meet the max flow capacity,” said Darrin Ruiz, northeast regional applications engineer for Xylem.

The updated design called for a bypass system that stayed within the same footprint as the original pumps. 

“Based on the specs, the footprint was very limited,” Ruiz said. 

Additionally, the pump station is located between Interstate 690 and Lake Onondaga and overlooks the New York State Fairgrounds, which hosts hundreds of events throughout the year. 

“It’s a high-visibility area, and loud diesel equipment would not have been appreciated,” Ruiz said.

Solution

To stay within the compact station area, Xylem used two Flygt N 3312 pumps that could plumb into the existing piping system, resulting in material cost savings for the customer. 

In addition to the pumps, the bypass system included three diesel-driven Godwin Dri-Prime CD300M pumps, which emit only 69 decibels at 30 ft, reducing noise pollution. 

“When the equipment is running at full speed, it’s hard to hear,” Ruiz said. “The highway in the background is actually louder than the equipment.” 

One Godwin CD300M pump was set up on grade and away from the construction area, and the other two serve as backups. 

The contractor and project owner also needed to be able to check that the system was running smoothly for the duration of the bypass, so a Godwin advanced remote monitoring and control panel was provided to continuously collect data from the variable frequency drive and transducer.

Results

The bypass system went online in March 2018 and ran continuously through September 2018. It was set up to emulate the response and flows of the plant’s permanent equipment, and remote connectivity enabled the various parties involved in the project to continually monitor the pumps from any location via a smart device.

The remote monitoring capability was especially helpful when the project began and fluctuations in the water flow varied widely due to the shifting student population at nearby Syracuse University. 

“Syracuse is a huge college town, so there were higher flows when school was in session, and then capacity dropped in the summer,” Ruiz said. “That’s the beauty of remote monitoring—we can watch the equipment and do troubleshooting as needed without having to be on site.” 

C.O. Falter Construction noted the ease with which anyone involved in the expansion and upgrade project could monitor the system in real time from remote locations. 

“It’s pretty slick,” said Dan Falter, project manager for C.O. Falter Construction. “If a pump goes down, we’re alerted even if we’re not on site. The remote monitoring capability provides peace of mind, which is everything.”

Along with flexibility and convenience, the remote monitoring and controls capabilities also proved more economical than traditional manned pump watch, providing a significant costs savings of nearly $57,000.

[Click here to visit Flygt's WWD Storefront]

A successful temporary bypass setup that operated continuously for seven months provided a reliable, cost-effective, long-term solution while crews expanded and upgraded the pump station. Additionally, the solution allowed the project owner and contractor to monitor flow rates and responses in real time from any location.

About the Author

Xylem Inc.

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.