Newark Completes Lead Service Line Replacement Program

Feb. 22, 2022
The lead service line program started in March 2019 with an 8-10 year timeline, but completed in February 2022.

The City of Newark’s Lead Service Line Replacement (LSLR) Program has completed nearly 24,000 replacements citywide in under 3 years at no cost to residents. On February 11, 2022, the city celebrated this project milestone with several prominent figures including Mayor Ras Baraka, Vice President Kamala Harris, EPA Administrator Michael Regan, and Governor Phil Murphy.

This effort to provide clean, safe, and reliable drinking water to all Newark residents initially began in March 2019 as an 8- to 10-year program. By September 2019, a $120 million bond from Essex County removed the cost for residents and the program’s timeline was reduced to three years. Newark was able to pivot from a public health crisis to a national model for other cities to follow for managing lead exposure in drinking water. This celebration comes on the heels of the Bipartisan Infrastructure Law that allocates $15 billion in federal funding for lead service line replacements and related activities across the country. 

As the program manager, CDM Smith was responsible for coordinating the individual replacements, tracking and sharing progress, filter distribution, and corrosion control treatment. This program also required careful coordination and communication between the city, consultants, contractors, and residents. As a community-based project built on trust and safety, great emphasis was placed to reach, educate, get buy-in, and develop employment opportunities for Newark residents.  

“My sincerest thanks to the City of Newark for letting CDM Smith partner in this program,” said Brian Farrelly, a construction manager at CDM Smith who managed day-to-day operations of the program. “Together, we have made a great accomplishment in under three years! Newark is a model for all cities and water supply agencies challenged with lead line replacement in the upcoming years.”

“We came here…to highlight what you have accomplished here in Newark as an example and a role model of what cities around our country are capable of doing, and I thank you for that,” said Vice President Harris at the event. 

“I’m proud to say [that] we recently completed an unprecedented, Herculean task of replacing all the city’s 24,000 lead service lines in less than three years,” Mayor Baraka wrote in the Newark Star-Ledger on February 10, 2022. “No other city has replaced as many lines as fast and we are being touted as the ‘model city’ for lead line abatement.”

For additional information, visit the city's project website: www.newarkleadserviceline.com.

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Chemical Plant Case Study

Aug. 14, 2024
Chemical Plant Gets a Fiberglass Conduit Upgrade

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.