Critical Repairs in LA: Bypass Solutions

Nov. 17, 2020

Comprehensive bypass solution resolves multiple challenges

About the author:

Nate Warren is senior sales engineer for Xylem. Warren can be reached at [email protected].

In Los Angeles, where one-fifth of the city’s water pipes were installed before 1931, deteriorating, leaking sewer lines are a regular occurrence. But when a section of the North Outfall Sewer (NOS) near the intersection of Avenue 19 and Humboldt Street in downtown Los Angeles threatened to collapse, swift action was needed.

Built in the early 1900s, the NOS passes through both residential and commercial neighborhoods in the central Los Angeles area. Due to its location, a sewer line break would be catastrophic. 

The NOS Unit 12 line is near the 110 and 5 freeways, right next to the LA River. It is also close to a high-voltage transmission tower and runs under the Metrolink commuter train tracks. 

Repairs on about a half-mile stretch of the 48-inch-wide pipe were planned for 2020, but the risk of a sinkhole under the train tracks meant fast-tracking the $20 million-plus project. In November 2018, the city of Los Angeles developed a contingency plan to provide emergency response services in the event of a sewage spill or further underground structural failures. Xylem Rental Solutions worked with the city and its contractor, Vido Artukovich & Sons, to implement the plan.

The greatest worry was if the void got worse, the transmission tower was in danger of collapsing and pulling power lines onto the 110 freeway. Once the contingency plan was developed, Xylem worked with Artukovich to develop a temporary sewer bypass system to route sewage around the repair site. 

Addressing Complex Project Challenges

Designing the temporary bypass system proved complicated since crews could not dig down to the deteriorating pipeline without threatening nearby infrastructure. When project planning got underway in January 2019, the Xylem team discovered the sewer pipeline was buried 50 feet deep, rather than 30 feet as initially thought. Designing and installing the suction pit for the bypass pumping operation was equally challenging because it was so deep. Xylem, with help from Artukovich & Sons, and the project manager Anthony Artukovich, had to incorporate a process to allow construction crew members to enter the pit to make sewer repairs without compromising safety.

The significant depth of the pit also meant installing steel support braces for reinforcement, narrowing the diameter of the pit; however, design specifications required adequate spacing between pumps to maintain proper flow. Without adequate space between them, the pumps would fight each other for flow. With the bypass pipeline pushing out into Avenue 19, a popular alternate route for those commuting to suburbs just north of Los Angeles like Burbank and Glendale, special considerations also had to be made to avoid disrupting traffic. 

Unusual Pump Configuration Maintains Water Flow

In spite of a multitude of challenges, Xylem, along with the help of Artukovich, designed and implemented a successful temporary bypass system. The system, which moves a peak flow of 40 million gallons per day (mgd), runs from Riverside Drive and San Fernando Road to Avenue 19 near Humboldt Street. 

As the main 40 mgd bypass system was being constructed, a 20-foot suction pit was excavated over the 35-foot deep sewer on Avenue 19 to stage Flygt 3531, 335HP, 24-inch electric submersible sewage pumps. The priming system is powered by a diesel air compressor, and Godwin GHPU90 power packs drive the submersible pumps. This solution allowed Xylem to install a 24 mgd pumping system in a small working area. 

The 40 mgd bypass system consisted of four Flygt 3531 electric submersible sewage pumps. Two pumps were primary, and two pumps were dedicated standby. Due to the space limitations, the Xylem team staged the pumps in an alternating pattern, making the first and third pumps the primary pumps and the second and fourth pumps the standby pumps. This unorthodox solution worked well to ensure proper flow was maintained. 

Four 2,500-foot lines of 24-inch HDPE pipe run from each pump to an alternate sewer trunk line called the Northeast Interceptor Sewer. Burying the pipe under the street ensured that traffic flow along Avenue 19 was not impeded. 

To meet fluctuating flow conditions and address ragging concerns, the Xylem team opted to mount the Flygt 3531 pumps on a slide rail system typically used in permanent pump system designs. In a standard bypass scenario, a special crane must be used to pull the piping and the pump at the same time. Each pump is fitted with a Godwin variable frequency drive (VFD) to optimize energy consumption and allow the pumps to automatically start and stop to maintain a consistent sewer level. Each VFD was networked together so that they all could be controlled by a Godwin Advanced Remote Monitoring control panel. The wireless technology provides remote monitoring and enabled control of the pump from any smartphone, tablet or desktop computer. 

The control panel also provided clog detection. When a pump started to clog the pump’s motor, amps would rise, and the flow would drop. The system would alert pump watch personnel who addressed the clog by following a step-by-step plan of backflushing the pump. The process took less than five minutes during which the standby pumps automatically started and took over pumping. Pump watch personnel lauded the ability to monitor the pump performance remotely so that when an issue is communicated—such as ragging requiring backflush—action could be taken quickly. Two diesel generators were set up to power the pumps, one to power the two submersible pumps and a second one to act as a standby. In the event that the primary generator failed, the standby generator would automatically start and take over supplying primary power to the bypass system.

Advertisement

Bypass Setup Provides Confidence, Peace of Mind

Following nearly seven months of planning and installation, sewer repair and rehabilitation activities began in June 2019. The temporary bypass setup was expected to operate continuously for nine months. 

The combination of reliable primary pumps, supported by backup pumps, a redundancy system and remote monitoring and control of the operation provided confidence and peace of mind for the city managers. By coming to the table with a custom solution complemented by remote technology, the city was provided a cost-effective and efficient option for a challenging sewer bypass project.

About the Author

Nate Warren

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.
Directory

Xylem Inc.

April 26, 2018