Sludge Solutions

Sept. 5, 2007

About the author: Dan Tumis is regional sales manager for Entech Design, Inc. He can be reached at 940/898-1173 or by e-mail at [email protected].

Entech Design, Inc. manufactures interface level analyzers for a variety of municipal and industrial process applications. Systems in the wastewater treatment industry provide measurement of sludge blanket levels in primary and secondary clarifiers and gravity thickeners.

The West Point Wastewater Treatment Plant (WWTP) in King County, Wash., recently used an Entech BinMinder 9300 ultrasonic sludge level analyzer to investigate improvements to sludge wasting in primary clarifiers. After confirming accurate and reliable measurements, West Point WWTP used the instrument to determine whether its existing sludge-wasting scheme was achieving stated goals. According to Hien Nguyen, process analyst for West Point, “The plant was looking for a reliable blanket-level measurement to help control sludge-wasting from their PLC [programmable logic controller] system.”

Out with the old

West Point currently measures sludge level over the sludge sump area in its rectangular clarifiers to maximize wasting. The blanket level is measured manually twice each day. From this information, plant personnel adjust pumping operation. The strategy is to maintain 2-ft sludge levels in primary clarifiers by increasing or decreasing the pump operation according to the infrequent manual measurements.

According to Nguyen, “If the blanket level is above 2 ft, pump operation is increased by 5%.

If the blanket level is below 2 ft, pump operation is decreased by 5%. No adjustments are made if the blanket level is 2 ft.”

In with the new

Five weeks of data from the new analyzer illustrated an obvious diurnal pattern, with the blanket level varying from a low of 2 ft to a high of 8 ft. It is fair to conclude that the current pump control routine does not effectively maintain the blanket level near the desired target level, presumably as a result of the infrequency of manual measurements and corresponding infrequency in adjusting pump operation.

By using BinMinder 9300, the plant found a cost-effective and reliable solution to problems associated with infrequent and otherwise unreliable manual sludge level measurements at West Point WWTP. The plant continues to explore more effective ways to waste sludge in conjunction with the sludge level analyzer.

Download: Here

About the Author

Dan Tumis

Sponsored Recommendations

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Meeting the Demands of Wastewater Treatment Plants

May 24, 2024
KAESER understands the important requirements wastewater treatment plant designers and operators consider when evaluating and selecting blowers and compressed air equipment. In...

Modernize OT Cybersecurity to Mitigate Risk

April 25, 2024
Rockwell Automation supports industry-leading Consumer Packaged Goods company, Church & Dwight, along their industrial cybersecurity journey.