Los Angeles to pay $20.8 million for discharging more than 12 million gallons of wastewater

Aug. 21, 2024
The City of Los Angeles will pay $20.8 million for discharging more than 12 million gallons of untreated wastewater into Santa Monica Bay.

The City of Los Angeles, California, has agreed to pay a total of $20.8 million to fix issues at the Hyperion Water Reclamation Plant and to complete related environmental projects in connection with the discharge of millions of gallons of wastewater into Santa Monica Bay in 2021.

Hyperion, the city’s oldest and largest wastewater treatment facility, collects, treats and disposes of wastewater for Los Angeles and several other municipalities, including Beverly Hills, Culver City, El Segundo, Santa Monica, San Fernando and West Hollywood. Hyperion’s service area includes more than 4 million people.

Hyperion treats an average of 260 MGD of wastewater, of which 225 million gallons are discharged through its 5-Mile Outfall to the Santa Monica Bay and 35 million gallons are conveyed to a water recycling facility for advanced treatment and reuse.

Treatment of wastewater begins in a portion of the facility called the Headworks area, which involves the use of bar screens to remove large objects such as branches, plastics and rags, from entering the wastewater.

In July 2021, the Headworks became inundated with debris, causing wastewater to flood that area.

Hyperion’s relief system was triggered and approximately 12.5 million gallons of untreated wastewater was discharged through the Facility’s 1-Mile Outfall into the Santa Monica Bay.

Offshore water quality testing and monitoring subsequently conducted around the 5-Mile Outfall showed exceedances of applicable water quality standards for total coliform bacteria, E. Coli and Enterococcus.

To resolve the U.S. Attorney’s criminal investigation, the city has agreed to spend no less than $20 million to perform and complete various projects at Hyperion, which the city agreed to perform under an Administrative Order On Consent previously issued by the U.S. Environmental Protection Agency (EPA).

That work includes improvements on Hyperion’s Distributed Control System, such as integrating bar screen, level sensors and other ancillary equipment, integrating the alarm or status screens software to removed antiquated alarms, training Hyperion operators responsible for control room operations on the updates and constructing high-level channel overflow manage improvements.

In addition, the city has agreed to continue and expand upon its water quality testing program in compliance with its permits and will add two additional water quality testing sights between Dockweiler Beach and King Harbor.

The city will also complete its rapid bacteria testing study and seek accreditation from the EPA so it can test for bacteria levels in ocean water on a more rapid basis.

The city will retain a qualified third-party auditor to conduct annual audits of Hyperion’s operations to determine whether it is in compliance with the work described above as well as the Clean Water Act.

Finally, the city has agreed to perform a one-year community outreach service project in coordination with the Los Angeles Sanitation and Environmental Department and a nonprofit.

That work will include meetings with local government officials and community members, developing an improved emergency communications plan, and coordinating educational outreach with residents and schools.

The cost of the additional monitoring, rapid bacteria testing study and the community outreach project is estimated to be no less than $800,000.

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.