Couplings Repair Pipe in Dundee, Fla.

Dec. 15, 2014

gas company bore into the ground in a residential area in Dundee, Fla. The boring went right through a 10-in. asbestos cement (AC) pipe, completely shattering it. The company called in the break to the municipality, as approximately 4,000 residents were cut off from water supply. 

When municipal foreman James Coker and his team arrived, they started by contracting out the excavation of the pipe, which was 3 ft deep. The break was significant enough that the damaged pipe had to be cut out and replaced with PVC pipe joined to the AC pipe with couplings at each end. 

The challenge was to repair the pipe quickly, restore water supply to thousands of residents and minimize damage to surrounding streets and properties. 

Coker used two HYMAX couplings to connect the PVC pipe on each end to the AC pipe.

The couplings presented three fundamental advantages for this repair: Ease of installation, as a result of a two-bolt top-facing design that is easy to secure and eliminates the need for under-pipe digging; a wide outside diameter range, allowing for a tight seal in spite of the differing pipe materials used; and durability, allowing for each connecting pipe end to flex four degrees, enabling continuous dynamic angular deflection. 

Once the damaged AC pipe was removed, a piece of PVC pipe was measured and cut to size. Coker’s crew loosened the couplings’ two-bolt enclosures and slid them onto each end of the pipe. Once the couplings were attached, the pipe was lowered into the ground, where the repair
was made. 

Download: Here

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Chemical Plant Case Study

Aug. 14, 2024
Chemical Plant Gets a Fiberglass Conduit Upgrade

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.